So if the contractor is to create subsystems, would they be given a base model of the building to place the subsystem in or would they be expected to create from scratch?
Anne-Marie Hyatt, KAD Construction, Inc.
Mark Mergenschroer, BIM Development Coordinator, TME, Inc.: They should be given the building, in my opinion. This is no different that a CAD background.
Member Comments
More Ask Our Experts Questions
- I would like to bid on a project but have no idea as to how or where to start (Dec 08, 2009)
- Please provide definitions, and uses, of the following square footage cost estimating modalities (Dec 07, 2009)
- ADA regulations for handicapped toilets (Dec 07, 2009)
- Price per square foot costs on building a warehouse (Dec 07, 2009)
- Is there a resource recommendation you would identify for writing a company SOP for hard bid? (Dec 02, 2009)
- RSMeans line item questions (Dec 02, 2009)
- Are there numbers for estimating the average costs asscociated with computer wiring? (Dec 02, 2009)
- Operating costs in the Heavy Construction Cost Data book (Dec 02, 2009)
- Do you need a roof permit in Jacksonville? (Dec 02, 2009)
- I need to forward drawings to you for a quote (Nov 20, 2009)
Got a question for our experts that's not listed? Submit it using the form below: