Arena Project Case Study in Illinois

This project information is pulled from our database of hundreds of thousands of construction projects that have been started over the past 5 years. Use it to research ideas and potential partners for your own project. Additional examples of arena projects in Illinois are also available.

Project Overview

Project Title:CHICAGO FIRE SOCCER STADIUM
Estimated Value:$70,000,000 (a more accurate cost estimate is available from RSMeans Online)
The cost to build arenas in Illinois depends upon the location, project scope, specific components used and current market conditions. If you are looking to size the cost of building a project similar to this one, an accurate estimate of the costs to build your particular project is available on RSMeansOnline.com.

Project Location

State:Illinois
County:Cook
City:Bridgeview
Address:7300 W 71st St

Project Type

Building Category:Arenas
Work Type:New

Project Description:

Arena 20,000 Seat Stadium, 1500 Club Seats, 28,000 Seats For Concerts, 40 Luxury Suites & 2 Party Suites The Facility Will House The Illinois Soccer Hall Of Fame & Will Contain A Socce Pub, Food Courts, Four Locker Rooms, Administrative Offices & Training Rooms

Project Owner

ANSCHUTZ ENTERTAINMENT GROUP
VILLAGE OF BRIDGEVIEW (Associate Owner)

Project Design & Engineering

Mechanical & Electrical Engineer: A EPSTEIN & SONS
Architect: ROSSETTI JORGENSON ASSOCIATES

Project Construction

Structural Steel Supplier: CIVES STEEL CO
Structural Steel Erector: CIVES STEEL CO
Concrete: GOEBEL FORMING INC
Underground Utilities: JOHN KENO & CO
Grading, Excavation, Hauling: LINDAHL BROS INC
Foundations, Pilings, Caissons: THATCHER ENGINEERING CORP