This project information is pulled from our database of hundreds of thousands of construction projects that have been started over the past 5 years. Use it to research ideas and potential partners for your own project. Additional examples of excavating & grading projects in North Carolina are also available.

Project Overview

Project Title:UNC CHAR DUKE POWER SUBSTATION PHSE I
Estimated Value:$713,700 (a more accurate cost estimate is available from RSMeans Online)
The cost to build substations in North Carolina depends upon the location, project scope, specific components used and current market conditions. If you are looking to size the cost of building a project similar to this one, an accurate estimate of the costs to build your particular project is available on RSMeansOnline.com.

Project Location

State:North Carolina
County:Mecklenburg
City:Charlotte
Address:Univ City Blvd

Project Type

Building Category:Substations, Electrical Work, Excavating & Grading
Work Type:New

Project Description:

Electrical Work, Excavating & Grading, Fencing, Power Stations The Work Includes The Installation Of 2 Pad Mounted 15kV SF6 Switchgear That Will Be Provided By The University, New Underground 15kV Cable And Ductbank, Ne 15kV Cable, Disconnects, Lighting Arresters And Cable Tray At Overhead Service, The Installation Of Lighting That Will Be Provided By The University, New Fencing And Stone For Switchyard, And All Trenching, Backfill, Seeding, Erosion Control And Paving Repairs For The Electrical Work, With All Appurtenances

Project Owner

UNIVERSITY OF NC - CHARLOTTE

Project Design & Engineering

Structural Engineer: Bulla Smith Design Engineering
Blue Printer: SHARPE IMAGES