Park Building Project Case Study in Michigan

This project information is pulled from our database of hundreds of thousands of construction projects that have been started over the past 5 years. Use it to research ideas and potential partners for your own project. Additional examples of park building projects in Michigan are also available.

Project Overview

Project Title:HURON VALLEY SWIM CLUB BATHHOUSE
Start Date:2005-09-01
Estimated Value:$300,000 - a more accurate cost estimate is available from RSMeans Online
The cost to build park buildings in Michigan depends upon the location, project scope, specific components used and current market conditions. If you are looking to size the cost of building a project similar to this one, an accurate estimate of the costs to build your particular project is available on RSMeansOnline.com.

Project Location

State:Michigan
County:Washtenaw
City:Ann Arbor
Address:4601 Park Rd

Project Type

Building Category:Park Buildings
Work Type:New

Project Description:

Park Building Concrete Slab On Grade Foundation, CMU Block Structural Frame, Concrete Block Exterior, Masonry Exterior , Pre-Manufactured Wood Truss Roof Structure Demolish Old Bathhouse & Build A New 4400 Sq Ft Bathhouse; 1400 Sq Ft For The Picnic Pavilion

Project Owner

Lincoln A. Poley Architect (Owner's Representative)

Project Design & Engineering

Mechanical & Electrical Engineer: ME ENGRG CONSULTANTS INC
Structural Engineer: STRUCTURAL DESIGN INC (SDI)

Project Construction

General Contractor: AZ SHMINA, INC