High School Square Foot Cost Estimates

The following estimate assumes face brick with concrete block back-up / steel frame, using 2013 RSMeans data.
National Cost Estimate (Union Labor) % of Total Cost Per SF Cost
Construction Total $122.48 $15,922,500
Contractor Fees (GC,Overhead,Profit) 25% $30.62 $3,980,600
Architectural Fees 6% $7.35 $955,400
Total Building Cost $160.45 $20,858,500

Building Products Used in High School Construction

Duralife Lockers® by Scranton Products
Scranton Products™, the leader of the high density polyethylene (HDPE) plastic and locker industry for over 26 years, has revolutionized the corridor locker. Introducing Duralife Lockers® – the only HDPE plastic locker that is fully fire-rated for your corridor application. Specially designed to meet the demands of the school environment, Duralife® Lockers are built to withstand the harshest daily use. Virtually maintenance free, HDPE outperforms metal lockers at a comparable price point, providing years of everyday low maintenance.
Documents Avaliable:
  Technical Datasheets vailable for download Technical Datasheets

Completed High School Projects

Featured High School Projects:


Choose from the States and Provinces below to find Local Completed High School Projects

View High School Construction Information by State/Province

View All Building Categories>>
Want more projects like this?


Get FREE Leads emailed to you each week!
Do you work on High Schools?