High School Square Foot Cost Estimates

The following estimate assumes face brick with concrete block back-up / steel frame in Fargo, ND, using 2013 RSMeans data.
Fargo, ND Cost Estimate (Union Labor) % of Total Cost Per SF Cost
Construction Total $105.33 $13,693,400
Contractor Fees (GC,Overhead,Profit) 25% $26.33 $3,423,300
Architectural Fees 6% $6.32 $821,600
Total Building Cost $137.99 $17,938,300
Cost Estimates for Other Cities in North Dakota

Building Products Used in High School Construction

Duralife Lockers® by Scranton Products
Scranton Products™, the leader of the high density polyethylene (HDPE) plastic and locker industry for over 26 years, has revolutionized the corridor locker. Introducing Duralife Lockers® – the only HDPE plastic locker that is fully fire-rated for your corridor application. Specially designed to meet the demands of the school environment, Duralife® Lockers are built to withstand the harshest daily use. Virtually maintenance free, HDPE outperforms metal lockers at a comparable price point, providing years of everyday low maintenance.
Documents Avaliable:
  Technical Datasheets vailable for download Technical Datasheets

Completed High School Projects in North Dakota

If you are looking for projects similar to this project, view a list of High School projects that have been built over the past five years.

Companies that Specialize in High Schools in North Dakota

ArchitectsView More Architects >>General Contractors

View High School Construction Information by State/Province

View All Building Categories>>
 Get More Upcoming Projects

IT'S FREE - GET STARTED!
Do you work on High Schools in North Dakota?