The following estimate assumes face brick with concrete block back-up / steel frame in Yellowknife, NT, using 2013 RSMeans data.
Yellowknife, NT Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Construction Total
$132.16
$17,180,400
Contractor Fees (GC,Overhead,Profit)
25%
$33.04
$4,295,100
Architectural Fees
6%
$7.93
$1,030,800
Total Building Cost
$173.13
$22,506,300
Building Products Used in High School Construction
Duralife Lockers® by Scranton Products Scranton Products™, the leader of the high density polyethylene (HDPE) plastic and locker industry for over 26 years, has revolutionized the corridor locker. Introducing Duralife Lockers® – the only HDPE plastic locker that is fully fire-rated for your corridor application. Specially designed to meet the demands of the school environment, Duralife® Lockers are built to withstand the harshest daily use. Virtually maintenance free, HDPE outperforms metal lockers at a comparable price point, providing years of everyday low maintenance.