Service & Gas Station Square Foot Cost Estimates
The following estimate assumes concrete block / wood joists in Columbus, OH, using 2013 RSMeans data.
| Columbus, OH Cost Estimate (Union Labor) | % of Total | Cost Per SF | Cost |
| Construction Total | | $85.37 | $853,700 |
| Contractor Fees (GC,Overhead,Profit) | 25% | $21.34 | $213,400 |
| Architectural Fees | 6% | $5.12 | $51,200 |
Total Building Cost | $111.83 | $1,118,300 |