This project information is pulled from our database of hundreds of thousands of construction projects that have been started over the past 5 years. Use it to research ideas and potential partners for your own project. Additional examples of municipal water and wastewater facility projects in Georgia are also available.
| Project Title: | LIBERTY PLACE PHASE I WATER & SEWER |
|---|---|
| Start Date: | 2004-05-01 |
| Estimated Value: | $1,000,000 - a more accurate cost estimate is available from RSMeans Online |
| State: | Georgia |
|---|---|
| County: | Liberty |
| Address: | Mid Coast Business Center |
| Building Category: | Municipal Water and Wastewater Facilities, Water and Sewage Piping, Excavating & Grading |
|---|---|
| Work Type: | Addition/Alteration |
Approx 5,112 LF 16" & 5,896 LF 12" Water Main, Appurtenances, approx 2,537 LF 8" & 5,064 LF 12" Force Main, Apprutenances, Construct 275 GPM Submersible Duplex Pump Station, 2,936 LF 10" & 159 LF 12" Gravity Sewer At Varying Depths