Municipal Water and Wastewater Facility Project Case Study in New York

This project information is pulled from our database of hundreds of thousands of construction projects that have been started over the past 5 years. Use it to research ideas and potential partners for your own project. Additional examples of municipal water and wastewater facility projects in New York are also available.

Project Overview

Project Title:LAKE STREET & POINT BREEZE PUMP STATIONS CONTRACT 79
Estimated Value:$6,248,300 (a more accurate cost estimate is available from RSMeans Online)
The cost to build municipal water and wastewater facilities in New York depends upon the location, project scope, specific components used and current market conditions. If you are looking to size the cost of building a project similar to this one, an accurate estimate of the costs to build your particular project is available on RSMeansOnline.com.

Project Location

State:New York
County:Erie
Address:Lake St & Old Lakeshore Rd

Project Type

Building Category:Municipal Water and Wastewater Facilities
Work Type:New

Project Description:

Water Treatment,Electrical Work,Sewage Treatment Demolition Of Pump Stations, Install Dry Wet Well Substructure, Control Building, Big Sister Creek STP Flow Control Chamber, Influent Pumping Station, Remove Force Mains, Connections, Pump Station Start Up, Performance Testing, Temporary Facilities, Site work, Grading, Instrumentation, Controls, Contract 79A-General/Mechanical; Contract 79B-HVAC; contract 79D-Electrical