IRON BRIDGE REGIONAL WATER RECLAMATION
This project information is pulled from our database of hundreds of thousands of historical construction projects. Help us build a complete case study of this project by adding information you know -- like issues encountered during construction, how your products were used.
Are you looking for current project leads (in planning stage or up for bid) to help grow your business? Then we can help!
Project Overview edit/contribute
| Project Type: | Water Treatment, Sewage Treatment |
| Work Type: | Alteration |
| Bid Date: | 2005-11-10 |
| Work Began: | 2005-12-01 |
Water Treatment, Sewage Treatment Modifications To The Two Existing 2-Mgal Flow Equalization Tanks; Modifications To The Four Exisitng Grit Units Including New Gates And Drop Boxes, Installatio Of new Baffle Walls, Mixers, Internal Recycle Pumps, Fine Bubble Diffused Aeration And Coarse Bubble Diffused Aeration In The Four Existing Bilogical Treatment Trains; Installation Of Four Centrifugal Blowers With A Blower Building; Replacing The Clarifier Suction Tube Withdrawal System With Spiral Scraper Mechanisms In Seven Of The Existing Clarifiers; Installation Of New Return And Waste Activated Sludge Pumps; Installation Of 3 Submersible Pumps In An Exsiting In-Plant Lift Station, Yard Piping, And All Necessary Electrical Power Systems And Instrumentation Systems To Provide A Complete, Functioning System
Project Participants edit/contribute
Project Location
| Address: | 601 Iron Bridge Circle Oviedo, FL 32764 |
| County: | Seminole |
More Florida construction projects are available via our Florida construction news and information page. Information on local building codes is available as well
CSI Categories Included in Project Scope
The following product types were used in this project. Click on any link to get more information on that product type from SmartBuilding Index -- including usage tips & techniques, product sourcing, manufacturer catalogs, formatted specs, CAD details and BIM objects.