| Details: | Water Treatment, Water Piping, Excavating & Grading, Sitework, Sewage Piping, Sewage Treatment The Work Consists Of Furnishing All Labor, Materials, &Equipment Required For The Installation Of Approximately 11,600 Linear Feet Of 6-Inch & 10-Inch PVC Potable Water Transmission Line, Including All Necessary Fittings, Valves, Connections To Existing Services, & All Other Work Required To Make The Water Transmission Line Replacement Fully Functional, The Work Also Includes The Installation Of A Valve Vault With 6" DIP, Valves, Actuators, & Miscellaneous Equipment As Well As Radio Transmitters & Other Electrical & Control Devices Used To Automate The Opening & Closing Of The Valves Based On Water Levels Detected In Two Water Storage Tanks, All Of Said Work Is To Be Done At The Places & In The Particular Locations, Of The Form, Sizes & Dimensions, Of The Materials, To The Lines & Grades, & At The Elevations |