| Details: | Electrical Work, Fencing, Sitework, Sewage Piping, Sewage Treatment Contract No. 1: Construction of a new 50,000 GPD wastewater treatment plant, expandable to 100,000 GPD, consisting of pre-screening system; a 50,000 GPD Sequencing Batch Reactor (SBR) system consisting of a Pre-Equalization basin, SBR basin, Post-Equalization basin, and aerobic digester; UV disinfection system; Control Building; plant lift station; site work; plant piping; electrical; emergency generator; and fence. Contract No. 2: Construction of 1,304 L.F. of 12 , 12,983 L.F. of 8 , 4,922 L.F. of 6 and 1,395 L.F. of 4 PVC gravity sewer pipe; 710 L.F. of 8 DIP gravity sewer pipe; 534 L.F. of 8 DIP and 149 L.F. of 4 DIP restrained joint gravity sewer pipe; 90 L.F. of 16 , 145 L.F. of 12 and 15 L.F. of 8 steel casing pipe, bore and jack; 95 new manholes; 95 service connections; and miscellaneous surface restoration. |