Estimating Tips for Common Work Results for Metals
Type 2 steel construction, commonly referred to as "simple construction", consists generally of field-bolted connections with lateral bracing supplied by other elements of the building, such as masonry walls or x-bracing. The estimator should be aware, however, that shop connections may be accomplished by welding or bolting. The method may be particular to the fabrication shop and may have an impact on the estimated cost.
Nuts, bolts, washers, connection angles, and plates can add a significant amount to both the tonnage of a structural steel job and the estimated cost. As a rule of thumb, add 10% to the total weight to account for these accessories.
Read more metals estimating tips.
![]() |