Construction Cost Estimates for Factory, 3 Story in Orlando, Florida

The following analysis estimates the cost to build a factory, 3 story for Orlando, Florida. Costs are derived from a building model that assumes basic components, using union labor for a 90000 square foot building.

Scope differences and market conditions can cause costs to vary significantly. To see an estimate of the costs to build a factory, 3 story in a different city or metropolitan area, go to our index of factory, 3 story models by state.

NOTE: This cost estimate uses 2013 RSMeans data. A more accurate estimate using current RSMeans cost data is available on RSMeans Online - our online cost estimating tool.

Factory, 3 Story Construction Cost Assumptions
Location: Orlando, Florida
Stories: 3
Story Height (L.F.): 12.00
Floor Area (S.F.): 90000
Basement Included: No
Data Release: Year 2013

Factory, 3 Story Square Foot Cost Assuming Face Brick Common Brick Back-up / Concrete Frame

Cost Estimate (Union Labor) % of Total Cost Per SF Cost
Total $88.81 $7,992,900
Contractor Fees (GC,Overhead,Profit) 25% $22.20 $1,998,200
Architectural Fees 6% $6.66 $599,500
Total Building Cost $117.67 $10,590,600
Cost Estimate (Open Shop) % of Total Cost Per SF Cost
Total $81.32 $7,318,900
Contractor Fees (GC,Overhead,Profit) 25% $20.33 $1,829,700
Architectural Fees 6% $6.10 $548,900
Total Building Cost $107.75 $9,697,500

Factory, 3 Story Square Foot Cost Assuming Face Brick Common Brick Back-up / Steel Frame

Cost Estimate (Union Labor) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--
Cost Estimate (Open Shop) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--

Factory, 3 Story Square Foot Cost Assuming Face Brick Concrete Block Back-up / Concrete Frame

Cost Estimate (Union Labor) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--
Cost Estimate (Open Shop) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--

Factory, 3 Story Square Foot Cost Assuming Face Brick Concrete Block Back-up / Steel Frame

Cost Estimate (Union Labor) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--
Cost Estimate (Open Shop) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--

Factory, 3 Story Square Foot Cost Assuming Stucco on Concrete Block / Concrete Frame

Cost Estimate (Union Labor) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--
Cost Estimate (Open Shop) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--

Factory, 3 Story Square Foot Cost Assuming Stucco on Concrete Block / Steel Frame

Cost Estimate (Union Labor) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--
Cost Estimate (Open Shop) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--