Construction Cost Estimates for High School in Selma, Alabama

The following analysis estimates the cost to build a high school for Selma, Alabama. Costs are derived from a building model that assumes basic components, using union labor for a 130000 square foot building.

Scope differences and market conditions can cause costs to vary significantly. To see an estimate of the costs to build a high school in a different city or metropolitan area, go to our index of high school models by state.

NOTE: This cost estimate uses 2013 RSMeans data. A more accurate estimate using current RSMeans cost data is available on RSMeans Online - our online cost estimating tool.

High School Construction Cost Assumptions
Location: Selma, Alabama
Stories: 2
Story Height (L.F.): 15.00
Floor Area (S.F.): 130000
Basement Included: No
Data Release: Year 2013

High School Square Foot Cost Assuming Decorative Concrete Block / R/Conc. Frame

Cost Estimate (Union Labor) % of Total Cost Per SF Cost
Total $90.48 $11,762,500
Contractor Fees (GC,Overhead,Profit) 25% $22.62 $2,940,600
Architectural Fees 7% $7.92 $1,029,200
Total Building Cost $121.02 $15,732,400
Cost Estimate (Open Shop) % of Total Cost Per SF Cost
Total $82.66 $10,746,400
Contractor Fees (GC,Overhead,Profit) 25% $20.67 $2,686,600
Architectural Fees 7% $7.23 $940,300
Total Building Cost $110.56 $14,373,300

High School Square Foot Cost Assuming Decorative Concrete Block / Steel Frame

Cost Estimate (Union Labor) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--
Cost Estimate (Open Shop) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--

High School Square Foot Cost Assuming Face Brick with Concrete Block Back-up / R/Conc. Frame

Cost Estimate (Union Labor) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--
Cost Estimate (Open Shop) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--

High School Square Foot Cost Assuming Face Brick with Concrete Block Back-up / Steel Frame

Cost Estimate (Union Labor) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--
Cost Estimate (Open Shop) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--

High School Square Foot Cost Assuming Limestone with Concrete Block Back-up / R/Conc. Frame

Cost Estimate (Union Labor) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--
Cost Estimate (Open Shop) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--

High School Square Foot Cost Assuming Limestone with Concrete Block Back-up / Steel Frame

Cost Estimate (Union Labor) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--
Cost Estimate (Open Shop) % of Total Cost Per SF Cost
Total Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost $---.-- $-,---,---.--