Construction Cost Estimates for High School in Roanoke, Virginia
The following analysis estimates the cost to build a high school for Roanoke, Virginia. Costs are derived from a building model that assumes basic components, using union labor for a 130000 square foot building.
Scope differences and market conditions can cause costs to vary significantly. To see an estimate of the costs to build a high school in a different city or metropolitan area, go to our index of high school models by state.
NOTE: This cost estimate uses 2013 RSMeans data. A more accurate estimate using current RSMeans cost data is available on RSMeans Online - our online cost estimating tool.
High School Construction Cost Assumptions
Location:
Roanoke, Virginia
Stories:
2
Story Height (L.F.):
15.00
Floor Area (S.F.):
130000
Basement Included:
No
Data Release:
Year 2013
High School Square Foot Cost Assuming Decorative Concrete Block / R/Conc. Frame
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
$101.02
$13,132,800
Contractor Fees (GC,Overhead,Profit)
25%
$25.26
$3,283,200
Architectural Fees
7%
$8.84
$1,149,100
Total Building Cost
$135.12
$17,565,100
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
$92.29
$11,998,300
Contractor Fees (GC,Overhead,Profit)
25%
$23.07
$2,999,600
Architectural Fees
7%
$8.08
$1,049,900
Total Building Cost
$123.44
$16,047,700
High School Square Foot Cost Assuming Decorative Concrete Block / Steel Frame
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
High School Square Foot Cost Assuming Face Brick with Concrete Block Back-up / R/Conc. Frame
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
High School Square Foot Cost Assuming Face Brick with Concrete Block Back-up / Steel Frame
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
High School Square Foot Cost Assuming Limestone with Concrete Block Back-up / R/Conc. Frame
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
High School Square Foot Cost Assuming Limestone with Concrete Block Back-up / Steel Frame