Construction Cost Estimates for Jr High School in Baltimore, Maryland
The following analysis estimates the cost to build a jr high school for Baltimore, Maryland. Costs are derived from a building model that assumes basic components, using union labor for a 110000 square foot building.
Scope differences and market conditions can cause costs to vary significantly. To see an estimate of the costs to build a jr high school in a different city or metropolitan area, go to our index of jr high school models by state.
NOTE: This cost estimate uses 2013 RSMeans data. A more accurate estimate using current RSMeans cost data is available on RSMeans Online - our online cost estimating tool.
Jr High School Construction Cost Assumptions
Location:
Baltimore, Maryland
Stories:
2
Story Height (L.F.):
15.00
Floor Area (S.F.):
110000
Basement Included:
No
Data Release:
Year 2013
Jr High School Square Foot Cost Assuming Concrete Block Stucco Face / Bearing Walls
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
$107.81
$11,859,400
Contractor Fees (GC,Overhead,Profit)
25%
$26.95
$2,964,800
Architectural Fees
7%
$9.43
$1,037,700
Total Building Cost
$144.20
$15,861,900
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
$99.48
$10,943,300
Contractor Fees (GC,Overhead,Profit)
25%
$24.87
$2,735,800
Architectural Fees
7%
$8.70
$957,500
Total Building Cost
$133.06
$14,636,700
Jr High School Square Foot Cost Assuming Concrete Block Stucco Face / Steel Frame
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Jr High School Square Foot Cost Assuming Decorative Concrete Block / Bearing Walls
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Jr High School Square Foot Cost Assuming Decorative Concrete Block / Steel Frame
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Jr High School Square Foot Cost Assuming Face Brick with Concrete Block Back-up / Bearing Walls
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Jr High School Square Foot Cost Assuming Face Brick with Concrete Block Back-up / Steel Frame