Construction Cost Estimates for Jr High School in Marion, Ohio
The following analysis estimates the cost to build a jr high school for Marion, Ohio. Costs are derived from a building model that assumes basic components, using union labor for a 110000 square foot building.
Scope differences and market conditions can cause costs to vary significantly. To see an estimate of the costs to build a jr high school in a different city or metropolitan area, go to our index of jr high school models by state.
NOTE: This cost estimate uses 2013 RSMeans data. A more accurate estimate using current RSMeans cost data is available on RSMeans Online - our online cost estimating tool.
Jr High School Construction Cost Assumptions
Location:
Marion, Ohio
Stories:
2
Story Height (L.F.):
15.00
Floor Area (S.F.):
110000
Basement Included:
No
Data Release:
Year 2013
Jr High School Square Foot Cost Assuming Concrete Block Stucco Face / Bearing Walls
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
$104.45
$11,489,600
Contractor Fees (GC,Overhead,Profit)
25%
$26.11
$2,872,400
Architectural Fees
7%
$9.14
$1,005,300
Total Building Cost
$139.70
$15,367,300
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
$96.38
$10,602,100
Contractor Fees (GC,Overhead,Profit)
25%
$24.10
$2,650,500
Architectural Fees
7%
$8.43
$927,700
Total Building Cost
$128.91
$14,180,300
Jr High School Square Foot Cost Assuming Concrete Block Stucco Face / Steel Frame
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Jr High School Square Foot Cost Assuming Decorative Concrete Block / Bearing Walls
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Jr High School Square Foot Cost Assuming Decorative Concrete Block / Steel Frame
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Jr High School Square Foot Cost Assuming Face Brick with Concrete Block Back-up / Bearing Walls
Cost Estimate (Union Labor)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Cost Estimate (Open Shop)
% of Total
Cost Per SF
Cost
Total
Interested in the complete estimate?
Contractor Fees (GC,Overhead,Profit)
Architectural Fees
Total Building Cost
$---.--
$-,---,---.--
Jr High School Square Foot Cost Assuming Face Brick with Concrete Block Back-up / Steel Frame